Project Updates

Project Update 4/16/2021

16 Apr 2021

/

wp4thst

Work completed this week: SW 7th Ave between SW 6th St to SW 7th St – Crews continued installing new Sidewalks & Driveways al ...

0
0

Project Update 4/15/2021

15 Apr 2021

/

wp4thst

Crews continue on SW 7th Ave between SW 6th St to SW 7th St grading along the new sidewalks & driveways. In Alleyway 2, crews ...

0
0

Project Update 4/14/2021

14 Apr 2021

/

wp4thst

Crews continue installing new sidewalks & driveways along SW 7th Ave between SW 6th St to SW 7th St. On SW 3rd Ct, crews cont ...

0
0