WORK COMPLETED TO DATE

  • The Contractor completed installation of the Project Identification Signs.
  • The Contractor passed out notices to upcoming work areas.
  • Staging Area was set up at the Northwest corner of SW 2nd St and SW 6th Ave. The Contractor had some equipment delivered on Thursday and Friday.

WORK SCHEDULED THIS WEEK: Monday, 06/22/2020 to Friday, 06/26/2020

  • The Contractor to begin work from SW 6th St & SW 14th Ave towards Auburn Ave. Activities will include setting up erosion control and MOT and clearing for installation of the new reclaimed water main. Survey Crew will begin staking for proposed RWM. Click here to view work area.
  • The Contractor will also begin working in Alleyway 3. Work will include installing any required Erosion Control, as well as begin any clearing work. Click here to view work area.