Project Update 7/2/2020

WORK COMPLETED THIS WEEK

  • Alleyways 2, 4, 5, 6 – Crews continued with initial clearing and grubbing of the Alleyways ahead of the proposed construction
  • Reclaimed Water Main (RWM) – Material delivery has been delayed
  • Crews saw cut pavement along Auburn Ave. in preparation for RWM
  • Fourth of July Holiday Observed – Friday, July 3rd is the observed Holiday, and no work is scheduled on the project.

WORK SCHEDULED NEXT WEEK

  • Alleyway 3 – Crews will begin excavation for the Alleyway Road base
  • Alleyway 7 – Initial clearing of debris/shrubs/trees to begin
  • Reclaimed Water Main – Material is scheduled to be delivered on Monday, July 6th and installation to begin on Tuesday July 7th. RWM to start at SW 6th St and SW 14th Ave and will proceed to the east towards Auburn Ave.

Alleyway 2 – Located between SW 6th St and SW 7th St and between SW 7th Ave and SW 8th Ave.
Alleyway 3 – Located between SW 3rd St and SW 4th St and between SW 7th Ave and SW 8th Ave.
Alleyway 4 – Located between SW 6th St and SW 7th St and between SW 6th Ave and SW 7th Ave.
Alleyway 7 – Located between SW 5th Ave and SW 6th Ave and between SW 2nd St to SW 4th St.

Aerial Overview from Drone
Aerial Overview from Drone
Aerial Overview from Drone

SHARE