Project Update 7/27/2020

WORK COMPLETED LAST WEEK

  • Alleyway 3 – Concrete Header Curbs are now 95% complete.
  • Alleyway 4 – Crews installed the 8” Rock Base, began framing for concrete header curbs, and began pouring concrete on the north end.
  • Alleyway 6 – Crews began excavation for the sub-grade.
  • Alleyway 7 – Crews completed the initial clearing.
  • Auburn Ave/SW 12th Ave (between Auburn Drive to SW 4th Street) – Crew completed installation of the 8” PVC Reclaimed Water Main.

WORK SCHEDULED THIS WEEK

  • SW 4th Street between SW 7th Ave to SW 12th Ave – Installation continues for the 8” PVC Reclaimed Water Main.
  • SW 4th Street between SW 7th Ave to SW 10th Ave – Crews will begin milling existing pavement and relaying the milled asphalt ahead of the RWM Installation Crew.
  • Alleyway 3 – Crews will begin pouring the new Pervious Concrete Pavement.
  • Alleyway 4 – Installation of 12” Header Curbs.
  • Alleyway 6 – Complete sub-base excavation/grading and begin placing the Base Rock.
  • Auburn Ave between Auburn Drive to SW 4th Street – Begin replacing the sidewalks which were removed during installation of the RWM and re-install the Bus Pad just south of SW 4th Ave.

Daily Lane Closures/Detours – Motorists can continue to expect minor delays along SW 4th Street between SW 7th Ave to SW 12th Ave. Please follow daily detour routes and watch for Flaggers in Work Zone Areas.

Alleyway 2 – Located between SW 6th St and SW 7th St and between SW 7th Ave and SW 8th Ave.
Alleyway 3 – Located between SW 3rd St and SW 4th St and between SW 7th Ave and SW 8th Ave.
Alleyway 4 – Located between SW 6th St and SW 7th St and between SW 6th Ave and SW 7th Ave.
Alleyway 7 – Located between SW 5th Ave and SW 6th Ave and between SW 2nd St to SW 4th St.