Project Update 10/14/2020

Crews continue are on SW 4th St between SW 7th Ave to SW 8th Ave preparing the roadway base for asphalt and also pouring the new sidewalks. Drainage crew continues installing new 18” drainage pipes on SW 7th Ave from SW 2nd St to the north.

More

Upcoming Intersection Improvements – Detour

Beginning Thursday 10/15/20 and Friday 10/16/20, crews will be reconstructing the intersection of SW 8th Ave and SW 4th St. This work is scheduled to take place between 9am to 3:30pm and will affect traffic on SW 8th Ave. Please follow the posted detour route during this time.

More

Project Update 10/13/2020

Crews continue with grading along SW 4th St between SW 7th Ave and SW 8th Ave for the new roadway. Crews also continue drainage work at SW 7th Ave at SW 2nd St. Testing and flushing of the new Reclaimed Water Main began today.

More

Project Update 10/12/2020

Crews continue work along SW 4th St between SW 7th Ave to SW 8th Ave placing the new 8” Base Rock and also pouring concrete sidewalks & driveways.

More

Project Update 10/9/2020

Work Completed this Week: SW 7th Ave from SW 2nd St to SW 2nd Court – New Drainage structures and 18” RCP Exfiltration Trench installed. SW 4th Street from SW 7th Ave to SW 8th Ave – Roadway Reconstruction continues with new curb & gutters installed, concrete driveways and sidewalks installed. Alleyway 2 – Pervious… Continue reading

More