Construction Begins June 15!

The SW 4th Street Neighborhood Improvement construction project is set to begin on 6/15/2020. Please follow the website, Facebook, or Twitter for project updates.

More

Project Update 4/22/2020

The first Pre-Construction meeting was held today, and the tentative start date for the project is set for June 15, 2020. Stay tuned for more information as it becomes available.

More

Public Notification Flyer

The City awarded the Construction Contract to Ric-Man Construction, Inc., and CEI Services to Baxter & Woodman, Inc. The City anticipates issuing Notice to Proceed to the Contractor on April 22, 2020. The Contractor anticipates mobilizing on the project site in early June 2020. For more information, please see the Public Notification Flyer. Check back… Continue reading

More

Project Update 3/16/2020

The construction contract has been awarded to Ric-Man Construction. Construction is anticipated to begin in June 2020.

More

Project Update 12/5/2019

The City anticipates award of the construction contract in January 2020. Construction start planned for Early 2020.

More

Bids Received

The City has received bids for the construction of the proposed improvements. The bids are under review.

More

Bids Due 10/4/2019

The City has advertised for bids from construction contractors. Bids are due on October 4, 2019. CLICK HERE for additional information.

More

Public Outreach Meeting 5/23/2019 Powerpoint

Thank you to all who attended the Public Outreach Meeting on May 23rd, 2019. If you were unable to attend the meeting and would like to view a .pdf of the presentation, please CLICK HERE to view.

More