Project Update 10/28/2020

Work continues along SW 7th Ave between SW 3rd St to SW 4th St installing new curb & gutters. Crews are also working at the intersection of SW 4th St and SW 7th Ave for the Pavement Reconstruction.

More

Project Update 10/27/2020

Crews are pouring the header curbs around the corners at SW 4th St and SW 8th Ave today and also along SW 7th Ave between SW 4th St to SW 3rd St for the new on street parking.

More

Project Update 10/26/2020

Crews continue working along SW 7th Ave between SW 4th St to SW 3rd St installing new curbs & gutters. Crews are also finishing up installing new drainage structures on SW 7th Ave between SW 1st St to SW 2nd St.

More

Project Update 10/23/2020

Work Completed this Week: SW 7th Ave from SW 2nd St to SW 1st St – Crews completed the 18” RCP Exfiltration Trench to Structure D-2A and installed new inlets D-1 & D-2. SW 4th Street from SW 7th Ave to SW 10th Ave – 1st lift of Asphalt was placed. SW 7th Ave from… Continue reading

More

Project Update 10/22/2020

The weather has finally cleared up and crews have began paving the 1st lift of asphalt along SW 4th St between SW 7th Ave to SW 10th Ave. Crew have also began pouring new curbs along SW 7th Ave between SW 4th St to SW 3rd St.

More

Project Update 10/21/2020

Due to weather, the Asphalt Paving along SW 4th St was cancelled today. Crews are working along SW 7th Ave between SW 1st St to SW 2nd St installing sewer cleanouts.

More

Project Update 10/20/2020

Crews continue installing new drainage along SW 7th Ave between SW 2nd St to SW 1st St. Also along SW 7th Ave, crews are beginning the roadway reconstruction between SW 4th St to SW 3rd St.

More

Project Update 10/19/2020

Crews continue working along SW 4th St between SW 7th Ave and SW 8th Ave grading the parkways. Crews are also beginning clearing work along the west side of SW 7th Ave just north of SW 4th St in preparation for the roadway reconstruction. Due to weather, the Drainage Crew is not working today.

More

Project Update 10/16/2020

Work Completed this Week: SW 7th Ave from SW 2nd St to SW 1st St – Crews continued installing the 18” RCP Exfiltration Trench. SW 4th Street from SW 7th Ave to SW 8th Ave – Roadway Reconstruction continues with fine grading the 8” Rock Base and installation of new Curbs & Gutters, Sidewalks and… Continue reading

More

Project Update 10/15/2020

Crews continue working along SW 4th St between SW 7th Ave and SW 8th Ave at the Roadway Reconstruction, as well as installing new sidewalks.