Project Update 9/17/2020

Crews continue pouring the Pervious Concrete in Alleyway 7 and also sidewalks along SW 4th St between SW 8th Ave to SW 10th Ave. Work also continues along SW 7th Ave between SW 2nd St to SW 3rd St as crew are begin installing new drainage structures and pipes.

More

Project Update 9/16/2020

Crew began pouring the Pervious Concrete in the north section Alleyway 7 today. Crews also continue pouring concrete driveways along SW 4th St between SW 8th Ave and SW 10th Ave. On SW 7th Ave crews continue installing the 8” PVC Reclaimed Water Main.

More

Project Update 9/15/2020

Crews continue pouring concrete sidewalks and driveways along SW 4th St and also at Alleyway 7 on SW 3rd St. Work along SW 7th Ave from SW 3rd St to SW 2nd St continues with installation of the 8” Reclaimed Water Main.

More

Project Update 9/14/2020

Work continues in Alleyway 7. Crews pouring header curbs and also backfilling behind the completed curbs. Work also continues along SW 7th Ave between SW 2nd St to SW 3rd St installing sanitary sewer laterals and work also continues along SW 4th St from SW 8th Ave to SW 10th Ave.

More

Project Update 9/11/2020

Work Completed this week: SW 7th Ave between SW 2nd Street to SW 3rd Street – Sanitary Sewer Main Replacement to be completed today, 9/11/2020. SW 4th Street between SW 8th Ave to SW 10th Ave – Sidewalk and Driveway removal and replacement started. Alleyway 7 South Section – Pervious Concrete now complete. Alleyway 7… Continue reading

More

Project Update 9/10/2020

Crews continue with pouring new sidewalk along SW 4th St from SW 8th Ave to SW 10th Ave and also began pouring the header curb in the North Section of Alleyway 7. The Sanitary Sewer Main replacement also continues on SW 7th Ave between SW 2nd St to SW 3rd St.

More

Project Update 9/9/2020

Crews today completed the Pervious Concrete in Alleyway 7 South Section and also began pouring new sidewalks and driveways along SW 4th St from SW 8th Ave to SW 10th Ave. Sanitary Sewer replacement continues along SW 7th Ave from SW 2nd St to SW 3rd St.

More

Project Update 9/8/2020

Today’s activities on the SW Neighborhood Project include placing the Pervious Concrete in Alleyway 7 South Section and placing the Base Rock on the North Section. Sanitary Sewer replacement continues on SW 7th Ave from SW2nd St to SW3rd St.

More

Project Update 9/4/2020

Work Completed this week: SW 7th Ave between SW 2nd Street to SW 3rd Street – Sanitary Sewer Main Replacement continued. Crews have completed from SW 2nd St to SW 2nd Court and are continuing south. SW 4th Street between SW 8th Ave to SW 10th Ave – Crews completed the excavation for the 12”… Continue reading

More

Project Update 9/3/2020

Today we have a short video of the activities taking place on the SW Neighborhood Improvement Project which includes Pervious Concrete in Alleyway 7, Pavement Reconstruction on SW 4th St and Sanitary Sewer Replacement on SW 7th Ave.

More