Project Update 4/19/2021

Crews continue working in SW 3rd Ct excavating for the new Rock Base. Along SW 6th St between SW 5th Ave to SW 8th Ave, crews continue grading for new sidewalks. Crews are also beginning to grade and install the bollards in Alleyway 4.

More

Project Update 4/19/2021

Crews continue working in SW 3rd Ct excavating for the new Rock Base. Along SW 6th St between SW 5th Ave to SW 8th Ave, crews continue grading for new sidewalks. Crews are also beginning to grade and install the bollards in Alleyway 4.

More

Project Update 4/19/2021

Crews continue working in SW 3rd Ct excavating for the new Rock Base. Along SW 6th St between SW 5th Ave to SW 8th Ave, crews continue grading for new sidewalks. Crews are also beginning to grade and install the bollards in Alleyway 4.

More

Project Update 4/16/2021

Work completed this week: SW 7th Ave between SW 6th St to SW 7th St – Crews continued installing new Sidewalks & Driveways along the West side. Crew also installed a few missing sewer clean outs. SW 3rd Ct between SW 8th Ave to SW 10th Ave – Excavation for new stabilized subgrade and placing… Continue reading

More

Project Update 4/15/2021

Crews continue on SW 7th Ave between SW 6th St to SW 7th St grading along the new sidewalks & driveways. In Alleyway 2, crews continue installation of the bollards at utility poles. In Alleyway 3, crews are making repairs to the pervious concrete.

More