Project Update 4/14/2021

Crews continue installing new sidewalks & driveways along SW 7th Ave between SW 6th St to SW 7th St. On SW 3rd Ct, crews continue with excavation and placing the new rock base. Crews are also installing the traffic bollards in Alleyway 2.

More

Project Update 4/14/2021

Crews continue installing new sidewalks & driveways along SW 7th Ave between SW 6th St to SW 7th St. On SW 3rd Ct, crews continue with excavation and placing the new rock base. Crews are also installing the traffic bollards in Alleyway 2.

More

Project Update 4/14/2021

Crews continue installing new sidewalks & driveways along SW 7th Ave between SW 6th St to SW 7th St. On SW 3rd Ct, crews continue with excavation and placing the new rock base. Crews are also installing the traffic bollards in Alleyway 2.

More

Project Update 4/13/2021

Crews continue with installing new Sidewalks & Driveways along SW 7th Ave south of SW 6th St. Excavation continues on SW 3rd Ct for the new Rock Base. Crews continue with final grading and installing bollards in Alleyway 2.

More

Project Update 4/12/2021

Crews began excavation for the new Rock Base on SW 3rd Ct today. Crews are also grading in Alleyway 2 and installing traffic bollards at Utility Poles. Along SW 7th Ave from SW 6th St to SW 7th St, crews are grading along the west side for new sidewalks.

More