Project Update 4/14/2021

Crews continue installing new sidewalks & driveways along SW 7th Ave between SW 6th St to SW 7th St. On SW 3rd Ct, crews continue with excavation and placing the new rock base. Crews are also installing the traffic bollards in Alleyway 2.

More

Project Update 4/14/2021

Crews continue installing new sidewalks & driveways along SW 7th Ave between SW 6th St to SW 7th St. On SW 3rd Ct, crews continue with excavation and placing the new rock base. Crews are also installing the traffic bollards in Alleyway 2.

More

Project Update 4/14/2021

Crews continue installing new sidewalks & driveways along SW 7th Ave between SW 6th St to SW 7th St. On SW 3rd Ct, crews continue with excavation and placing the new rock base. Crews are also installing the traffic bollards in Alleyway 2.

More

Project Update 4/13/2021

Crews continue with installing new Sidewalks & Driveways along SW 7th Ave south of SW 6th St. Excavation continues on SW 3rd Ct for the new Rock Base. Crews continue with final grading and installing bollards in Alleyway 2.

More

Project Update 4/12/2021

Crews began excavation for the new Rock Base on SW 3rd Ct today. Crews are also grading in Alleyway 2 and installing traffic bollards at Utility Poles. Along SW 7th Ave from SW 6th St to SW 7th St, crews are grading along the west side for new sidewalks.

More

Project Update 4/9/2021

Work completed this week: SW 7th Ave between SW 4th St to SW 6th St – Crews paved the 1st lift of new asphalt. SW 7th Ave between SW 6th St to SW 7th St – Crews began excavation along the west side for the new proposed sidewalk. SW 3rd Ct between SW 8th Ave… Continue reading

More

Project Update 4/8/2021

Crews continue installing new concrete sidewalks & driveways on SW 6th St between SW 5th Ave to SW 8th Ave.

More

Project Update 4/7/2021

Crews placed the 1st lift of Asphalt on SW 7th Ave between SW 4th St to SW 6th St. Work also continues along SW 6th St between SW 5th Ave to SW 8th Ave preparing areas for new sidewalks.

More

Project Update 4/6/2021

Installation of new concrete curbs, sidewalks & driveways continues along SW 6th St between SW 5th Ave to SW 7th Ave. The 1st lift of new asphalt is also scheduled for tomorrow on SW 7th Ave between SW 4th St to SW 6th St.

More

Project Update 4/5/2021

Crews continue installing new concrete sidewalks along SW 6th St between SW 5th Ave to SW 8th Ave. Crews are also setting up for the pressure test for the new Reclaimed Watermain on SW 4th St between SW 7th Ave to SE 1st Ave.

More