Project Update 4/1/2021

Work completed this week: SW 7th Ave between SW 4th St to SW 6th St – Section is ready for 1st lift of asphalt. SW 7th Ave between SW 6th St to SW 7th St – Crews began clearing for new sidewalks along the West side. SW 3rd Ct between SW 8th Ave to SW… Continue reading

More

Project Update 3/31/2021

Crews are lining an existing sanitary sewer today at SW 7th Ave and SW 2nd St. Work along SW 6th St continues with crews backfilling along the new sidewalks & driveways. Crews also began flushing the Reclaimed Watermain between SW 7th Ave to SE 1st Ave along SW 4th St.

More

Project Update 3/30/2021

Work continues along SW 6th St between SW 5th Ave to SW 8th Ave pouring concrete sidewalks & driveways and also placing the new Rock Base. On SW 4th St between SW 8th Ave to SW 10th Ave, crews are lining an existing sanitary sewer.

More

Project Update 3/29/2021

Crews continue new concrete sidewalk & driveway installation, as well as excavation for the new rock base along SW 6th St between SW 5th Ave to SW 8th Ave.

More

Project Update 3/29/2021

Crews continue new concrete sidewalk & driveway installation, as well as excavation for the new rock base along SW 6th St between SW 5th Ave to SW 8th Ave.

More

Project Update 3/26/2021

Work completed this week: SW 7th Ave between SW 4th St to SW 6th St – New 8” Rock Base completed and graded in preparation for the 1st lift of Asphalt. SW 3rd Ct between SW 8th Ave to SW 10th Ave – Crews completed installing the new 8” Watermain. SW 6th St between SW… Continue reading

More

Project Update 3/26/2021

Work completed this week: SW 7th Ave between SW 4th St to SW 6th St – New 8” Rock Base completed and graded in preparation for the 1st lift of Asphalt. SW 3rd Ct between SW 8th Ave to SW 10th Ave – Crews completed installing the new 8” Watermain. SW 6th St between SW… Continue reading

More

Project Update 3/26/2021

Work completed this week: SW 7th Ave between SW 4th St to SW 6th St – New 8” Rock Base completed and graded in preparation for the 1st lift of Asphalt. SW 3rd Ct between SW 8th Ave to SW 10th Ave – Crews completed installing the new 8” Watermain. SW 6th St between SW… Continue reading

More

Project Update 3/25/2021

Crews continue pavement reconstruction along SW 6th St from SW 5th Ave to SW 8th Ave and pouring new sidewalks & driveways. SW 7th Ave is also getting graded for the 1st lift of asphalt. Crews continue with Sewer Lining on SW 4th St.

More

Project Update 3/25/2021

Crews continue pavement reconstruction along SW 6th St from SW 5th Ave to SW 8th Ave and pouring new sidewalks & driveways. SW 7th Ave is also getting graded for the 1st lift of asphalt. Crews continue with Sewer Lining on SW 4th St.

More